Grove Pool Project

Great news! The Grove Family & Quiet Pools and Spas are getting a makeover! The approved renovation includes new plaster, waterline tile, mastic, and coping. Coping will not be replaced at the spas as they are in good condition!

  • 10/16/25 - Project (minus coping at the spas) was approved.

  • 11/20/25 - Approval was amended to include new coping throughout the entire family pool.

  • 3/9/26 Facility Closure Begins. Anticipated reopening June 1, 2026.

  • 3/9/26 Water being drained.

  • 3/13/26 Coping, waterline tile, and beach entry tiles removed.

  • 3/19/26 Quiet Spa regrout and mastic replacement, and spa fountain removal approved

  • 4/6/26 - Installation of coping on Quiet Pool commenced

  • 4/13/26 - Installation of coping on Family Pool and waterline tile at Quiet Pool and Family Spa commenced

Project Schedule (Tentative)

  • March 9, 2026

    Key fobs for access to the Grove facilities turned off

  • Week of March 9, 2026
    Drain pools and spas, and demolition of coping, tile and plaster

  • Week of April 6, 2026
    Install new coping on Quiet Pool

  • Week of April 13, 2026
    Install tile on Quiet Pool and repair coping on Family Spa

  • Week of April 20, 2026
    Install tile on Family Spa, and install coping on Family Pool  

  • Week of May 4, 2026
    Install Quiet Spa coping and tile, and install Family Pool tile

  • Week of May 18, 2026
    Pre‑plaster inspection followed by plaster application and system startup

  • Week of May 25, 2026
    Plaster startup and curing period (30 days minimum)

  • Week of June 8, 2026
    Final inspection, heating system activation, and turnover to the facility for reopening