Grove Pool Project

Great news! The Grove Family & Quiet Pools and Spas are getting a makeover! The approved renovation includes new plaster, waterline tile, mastic, and coping. Coping will not be replaced at the spas as they are in good condition!

  • 10/16/25 - Project (minus coping at the spas) was approved.

  • 11/20/25 - Approval was amended to include new coping throughout the entire family pool.

  • 3/9/26 Facility Closure Begins. Anticipated reopening June 1, 2026.

  • 3/9/26 Water being drained.

  • 3/13/26 Coping, waterline tile, and beach entry tiles removed.

  • 3/19/26 Quiet Spa regrout and mastic replacement, and spa fountain removal approved

  • 4/6/26 - Installation of coping on Quiet Pool commenced

  • 4/13/26 - Installation of coping on Family Pool and waterline tile at Quiet Pool and Family Spa commenced

  • 5/5/26 - Installation of coping and waterline tile is almost complete!

  • 5/20/26: The Grove pool facilities passed its pre-plaster inspection yesterday! This clears the way for plaster installation at the Quiet Pool, Quiet Spa, and Family Spa this Friday. These bodies of water are expected to be refilled by Tuesday, 5/26/26.

  • The final coping stones for the Family Pool are scheduled for installation next week, with plaster anticipated to be completed by late next week. Once the Family Pool is refilled, the required 30‑day curing period will begin.

  • Assuming all bodies of water pass final inspection with the Health Department, we are currently targeting an opening in approximately 5–6 weeks!

  • 5/27/26: All coping stones were installed in the Grove Family Pool, which means that the plaster can be installed and water can be filled back into the pool!

  • 6/1/26: The Grove pool is almost full! Aquatic brought in an IRWD water meter pump to help the pool fill quickly over this past weekend! The Health Department final inspection is tentatively scheduled for 6/16/26. If the Health Department approves the final inspection, the pools may open early without heat for approximately 1-2 weeks. The spas may be heated sooner.

Project Schedule (Tentative)

  • March 9, 2026

    Key fobs for access to the Grove facilities turned off

  • Week of March 9, 2026
    Drain pools and spas, and demolition of coping, tile and plaster

  • Week of April 6, 2026
    Install new coping on Quiet Pool

  • Week of April 13, 2026
    Install tile on Quiet Pool and repair coping on Family Spa

  • Week of April 20, 2026
    Install tile on Family Spa, and install coping on Family Pool  

  • Week of May 4, 2026
    Install Quiet Spa coping and tile, and install Family Pool tile

  • Week of May 18, 2026
    Pre‑plaster inspection followed by plaster application and system startup

  • Week of May 25, 2026
    Plaster startup and curing period (30 days minimum)

  • Week of June 14, 2026
    Final inspection, heating system activation, and turnover to the facility for reopening