Grove Pool Project
Great news! The Grove Family & Quiet Pools and Spas are getting a makeover! The approved renovation includes new plaster, waterline tile, mastic, and coping. Coping will not be replaced at the spas as they are in good condition!
10/16/25 - Project (minus coping at the spas) was approved.
11/20/25 - Approval was amended to include new coping throughout the entire family pool.
3/9/26 Facility Closure Begins. Anticipated reopening June 1, 2026.
3/9/26 Water being drained.
3/13/26 Coping, waterline tile, and beach entry tiles removed.
3/19/26 Quiet Spa regrout and mastic replacement, and spa fountain removal approved
4/6/26 - Installation of coping on Quiet Pool commenced
4/13/26 - Installation of coping on Family Pool and waterline tile at Quiet Pool and Family Spa commenced
Project Schedule (Tentative)
March 9, 2026
Key fobs for access to the Grove facilities turned off
Week of March 9, 2026
Drain pools and spas, and demolition of coping, tile and plasterWeek of April 6, 2026
Install new coping on Quiet PoolWeek of April 13, 2026
Install tile on Quiet Pool and repair coping on Family SpaWeek of April 20, 2026
Install tile on Family Spa, and install coping on Family PoolWeek of May 4, 2026
Install Quiet Spa coping and tile, and install Family Pool tileWeek of May 18, 2026
Pre‑plaster inspection followed by plaster application and system startupWeek of May 25, 2026
Plaster startup and curing period (30 days minimum)Week of June 8, 2026
Final inspection, heating system activation, and turnover to the facility for reopening