Arbors Club Project

Great news! The Arbors Family Pool, Spa, and Wader are getting a makeover! The approved renovation includes new plaster, waterline tile, mastic, and coping.

  • 11/20/25 - New plaster, waterline tile and coping project approved for the Arbors Pool, Spa, and Wader

  • 1/20/26 - The Association just received permits and approval on Tuesday, January 20, 2026! Work is scheduled to begin next week, with an anticipated completion at the end of March. During this time, the pool area will be closed for construction. Residents identified in the pool area during closure may be subject to enforcement action.

     Project Schedule (Tentative)

    • January 23, 2026

    Key fobs for access to the Arbors facilities will be turned off at 5:00PM PST.

    • January 24, 2026
      Installation of sump pumps to begin draining the bodies of water

    • Week of January 26, 2026
      Demolition of existing plaster, tile, and related materials

    • Week of February 2, 2026
      Step and trim tile installation

    • Week of February 9, 2026
      Delivery of materials to the project site

    • Week of February 16, 2026
      Coping and waterline tile installation
      (Pending receipt of coping materials)

    • Week of February 23, 2026
      Pre‑plaster inspection followed by plaster application and system startup

    • Week of March 2, 2026
      Plaster startup and curing period (30 days minimum)

    • Week of March 30, 2026*
      Final inspection, heating system activation, and turnover to the facility for reopening

    Please note that all dates are approximate and may shift based on weather, material availability, and inspection timelines. The Association is also dependent on the County Health Department for final approval to reopen the pool. Their inspection schedule may cause delays that are outside of the Association’s control.